JULY-DECEMBER 2020

SEPTEMBER 14, 2020 

The students are loving the reconstructed Sheridan Middle School which opened to the students this fall! Take a look inside by clicking on the video below.

SEPTEMBER 15, 2020 

The Sheridan School District has begun construction on the Sheridan High School Science and Art Addition. The following construction activities are taking place:

  • Building pad is completed. (included a 3 ½’ undercut on the entire building pad)

  • Footings are in progress

  • Underground rough-in for plumbing and electrical is in progress

  • Storm drainage is in progress

  • Building pad will be poured in a few weeks

  • Structural steel will deliver in a few weeks

The Sheridan School plans to get started on the Sheridan Support Services and Bus Facility next week.